ITAC Assessment: MA0045
ITAC logo
ITAC Assessment: MA0045
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product COATING OF METAL PARTS
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $1
M
to 5
M
# of Employees 35
Plant Area
n/a
Annual Production 2,080
Tgal
Production Hrs. Annual 3,120
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,976 745,897
kWh
Natural Gas $1,258 181
MMBtu
Fuel Oil #4 $10,324 1,675
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,679 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,622

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #4 Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $787 $450 $787
9,965
kWh
- - -
02 2.2437: Recover waste heat from equipment $756 $750 - - $756
-
MMBtu
-
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $5,100 $5,110 $7,887
99,941
kWh
$(-2,787.0)
-
MMBtu
- -
04 2.2511: Insulate bare equipment $1,515 $2,816 - $1,515
-
MMBtu
- -
05 2.2437: Recover waste heat from equipment $4,896 $7,546 $(-116.0)
(-1,465)
kWh
- $5,012
-
MMBtu
-
06 2.2113: Repair or replace steam traps $661 $500 - - $661
-
MMBtu
-
07 2.6212: Turn off equipment during breaks, reduce operating time $573 $11 $65
879
kWh
- $508
-
MMBtu
-
08 2.1311: Replace electrically-operated equipment with fossil fuel equipment $546 $1,329 $695
8,792
kWh
$(-250.0)
-
MMBtu
- $101
09 2.1233: Analyze flue gas for proper air/fuel ratio $845 $1,100 - - $845
-
MMBtu
-
TOTAL RECOMMENDED $15,679 $19,612 $9,318
118,112
kWh
$(-1,522.0)
-
MMBtu
$7,782
-
MMBtu
$101
TOTAL IMPLEMENTED $3,622 $2,811 $852
10,844
kWh
- $2,770
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #4 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs