| Assessment Year | 1985 |
|---|---|
| Principal Product | PAPER & COATED PAPER |
| NAICS |
n/a
|
| SIC | 2621: Paper Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
n/a
|
| Annual Production | 26,900
ton
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $572,038 | 8,305,100 |
kWh
|
$0.069 |
| Other Energy | $1,100,000 | 209,700 |
MMBtu
|
$5.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $151,746 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $61,532 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Paper Savings | Other Energy Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.6125: Sell combustible waste | $71,743 | - | - |
$12,743
-
MMBtu
|
- | $59,000 | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,606 | $440 |
$3,606
51,583
kWh
|
- | - | - | |
| 03 | 2.2511: Insulate bare equipment | $9,021 | $4,221 | - | - |
$9,021
-
MMBtu
|
- | |
| 04 | 2.2532: Use only amount of air necessary to prevent explosion hazard | $11,988 | $130 |
$1,328
19,343
kWh
|
- |
$10,660
-
MMBtu
|
- | |
| 05 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $6,483 | $1,300 |
$6,483
94,080
kWh
|
- | - | - | |
| 06 | 2.2113: Repair or replace steam traps | $47,000 | $640 | - | - |
$47,000
-
MMBtu
|
- | |
| 07 | 2.2136: Install / repair insulation on steam lines | $1,905 | $642 | - | - |
$1,905
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $151,746 | $7,373 |
$11,417
165,006
kWh
|
$12,743
-
MMBtu
|
$68,586
-
MMBtu
|
$59,000 | ||
| TOTAL IMPLEMENTED | $61,532 | $5,943 |
$3,606
51,583
kWh
|
- |
$57,926
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Paper Savings | Other Energy Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs