ITAC Assessment: MA0008
ITAC logo
ITAC Assessment: MA0008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product ELECTRONIC COILS
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 180
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 3,150
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $28,294 383,060
kWh
Natural Gas $12,743 2,086
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,095 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $702

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6214: Shut off pilots in standby equipment $79 - - $79
-
MMBtu
02 2.2511: Insulate bare equipment $359 $209 $359
4,982
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,034 $90 $1,034
14,068
kWh
-
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $623 $1,079 $1,179
16,120
kWh
$(-556.0)
-
MMBtu
TOTAL RECOMMENDED $2,095 $1,378 $2,572
35,170
kWh
$(-477.0)
-
MMBtu
TOTAL IMPLEMENTED $702 $1,079 $1,179
16,120
kWh
$(-477.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs