Assessment Year | 1984 |
---|---|
Principal Product | ANODIZING OF METALS |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 35 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 5,160
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,355 | 599,941 |
kWh
|
$0.081 |
Natural Gas | $78,669 | 11,467 |
MMBtu
|
$6.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,908 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,908 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,297 | $400 | - |
$3,297
-
MMBtu
|
|
02 | 2.2511: Insulate bare equipment | $2,850 | $1,872 | - |
$2,850
-
MMBtu
|
|
03 | 2.2113: Repair or replace steam traps | $4,985 | $1,125 | - |
$4,985
-
MMBtu
|
|
04 | 2.7111: Reduce illumination to minimum necessary levels | $776 | $125 |
$776
9,672
kWh
|
- | |
TOTAL RECOMMENDED | $11,908 | $3,522 |
$776
9,672
kWh
|
$11,132
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,908 | $3,522 |
$776
9,672
kWh
|
$11,132
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs