| Assessment Year | 2026 |
|---|---|
| Principal Product | General Medical and Surgical Services |
| NAICS | 622110: General Medical and Surgical Hospitals |
| SIC | 8062: General Medical and Surgical Hospitals |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
38,000
ft2
|
| Annual Production | 20,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $140,060 | 2,008,981 |
kWh
|
$0.070 | |
| Electricity Demand | $83,859 | 4,930 |
kW-mo/yr
|
$17.01 | |
| Electricity Fees | $22,691 | - |
|
- | |
| Natural Gas | $32,619 | 2,532 |
MMBtu
|
$12.88 | |
| Other Gas | $1,961 | 1 |
MMBtu
|
$1,961.16 | |
| Waste Disposal Costs | |||||
| Water Usage | $4,191 | 847 |
Tgal
|
$4.95 | |
| Water Disposal | $4,915 | 847 |
Tgal
|
$5.80 | |
| Other Liquid (non-haz) | $891 | 1 |
gal
|
$890.51 | |
| TOTAL YEARLY COSTS | $291,187 | ||||
| RECOMMENDED SAVINGS* | $21,905 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2625: Chill water to the highest temperature possible | $316 | - |
$7
99
kWh
|
- |
$309
-
MMBtu
|
|
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $20,687 | $9,761 |
$20,687
295,533
kWh
|
- | - | |
| 03 | 2.7134: Use photocell controls | $383 | $393 |
$383
5,475
kWh
|
- | - | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $519 | $5,750 |
$377
5,384
kWh
|
$15
-
kW-mo/yr
|
$127
-
MMBtu
|
|
| TOTAL RECOMMENDED | $21,905 | $15,903 |
$21,454
306,491
kWh
|
$15
-
kW-mo/yr
|
$436
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs