ITAC Assessment: LT8408
ITAC logo
ITAC Assessment: LT8408
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Marina
NAICS 713930: Marinas
SIC 4493: Marinas
Sales Range less than $500
k
# of Employees 5
Plant Area 2,000
ft2
Annual Production 1
units
Production Hrs. Annual 5,278
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,135 317,372
kWh
Electricity Demand $3,606 720
kW-mo/yr
Electricity Fees $6,481 -
TOTAL YEARLY COSTS $48,222
RECOMMENDED SAVINGS* $2,004 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7134: Use photocell controls $627 $283 $627
5,212
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,249 $3,600 $1,172
9,754
kWh
$77
-
kW-mo/yr
03 2.6211: Conserve energy by efficient use of vending machines $128 $598 $122
1,011
kWh
$7
-
kW-mo/yr
TOTAL RECOMMENDED $2,004 $4,481 $1,920
15,977
kWh
$84
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs