| Assessment Year | 2024 |
|---|---|
| Principal Product | Frozen Drink Machines |
| NAICS | 423990: Other Miscellaneous Durable Goods Merchant Wholesalers |
| SIC | 5099: Durable Goods, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 40 |
| Plant Area |
50,000
ft2
|
| Annual Production | 3,600
units
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $55,809 | 510,482 |
kWh
|
$0.11 | |
| Electricity Demand | $2,340 | 851 |
kW-mo/yr
|
$2.75 | |
| Waste Disposal Costs | |||||
| Water Usage | $888 | 117 |
Tgal
|
$7.61 | |
| Water Disposal | $1,323 | 117 |
Tgal
|
$11.33 | |
| TOTAL YEARLY COSTS | $60,359 | ||||
| RECOMMENDED SAVINGS* | $19,622 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,937 | $4,003 |
$17,937
164,109
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $416 | $2,298 |
$380
3,478
kWh
|
$36
-
kW-mo/yr
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $1,111 | $888 |
$1,039
9,510
kWh
|
$88
-
kW-mo/yr
|
$(-16.1) | |
| 04 | 2.7135: Install occupancy sensors | $158 | $63 |
$138
1,264
kWh
|
$20
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $19,622 | $7,252 |
$19,495
178,360
kWh
|
$143
-
kW-mo/yr
|
$(-16.1) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs