ITAC Assessment: LT8394
ITAC logo
ITAC Assessment: LT8394
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Marine Winches
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 50,000
ft2
Annual Production 1,920
units
Production Hrs. Annual 2,800
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,199 486,560
kWh
Electricity Demand $32,949 2,596
kW-mo/yr
Waste Disposal Costs
Water Usage $2,003 626
Tgal
Water Disposal $1,943 626
Tgal
TOTAL YEARLY COSTS $75,094
RECOMMENDED SAVINGS* $13,380 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,127 $2,110 $1,127
7,617
kWh
- -
02 2.6218: Turn off equipment when not in use $976 $888 $515
6,521
kWh
$477
-
kW-mo/yr
$(-16.1)
03 4.426: Modify workload $11,276 $320 $11,276
11,276
kWh
- -
TOTAL RECOMMENDED $13,380 $3,318 $12,919
25,413
kWh
$477
-
kW-mo/yr
$(-16.1)
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs