| Assessment Year | 2024 |
|---|---|
| Principal Product | Butt-welding fitting |
| NAICS | 332996: Fabricated Pipe and Pipe Fitting Manufacturing |
| SIC | 3317: Steel Pipe and Tubes |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
522,567
ft2
|
| Annual Production | 73,535,756
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $231,768 | 2,280,240 |
kWh
|
$0.10 | |
| Electricity Demand | $189,023 | 16,509 |
kW-mo/yr
|
$11.45 | |
| Natural Gas | $290,347 | 61,812 |
MMBtu
|
$4.70 | |
| Other Gas | $196,535 | 1 |
MMBtu
|
$196,535.27 | |
| Waste Disposal Costs | |||||
| Water Usage | $15,189 | 2,173 |
Tgal
|
$6.99 | |
| TOTAL YEARLY COSTS | $922,863 | ||||
| RECOMMENDED SAVINGS* | $12,689 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,294 | $3,694 |
$3,741
36,821
kWh
|
$1,553
-
kW-mo/yr
|
- | |
| 02 | 2.6218: Turn off equipment when not in use | $2,420 | $2,019 |
$1,488
14,645
kWh
|
$967
-
kW-mo/yr
|
$(-35.4) | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,975 | $1,150 |
$4,975
48,964
kWh
|
- | - | |
| TOTAL RECOMMENDED | $12,689 | $6,863 |
$10,204
100,430
kWh
|
$2,521
-
kW-mo/yr
|
$(-35.4) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs