ITAC Assessment: LT8387
ITAC logo
ITAC Assessment: LT8387
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product telecommunication
NAICS 517410: Satellite Telecommunications
SIC 3669: Communications Equipment, Not Elsewhere Classified
Sales Range $500
k
to 1
M
# of Employees 25
Plant Area 66,500
ft2
Annual Production 1
units
Production Hrs. Annual 2,340
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,364 1,334,250
kWh
Electricity Demand $37,205 2,745
kW-mo/yr
Electricity Fees $11,011 -
TOTAL YEARLY COSTS $133,580
RECOMMENDED SAVINGS* $8,725 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7224: Reduce space conditioning during non-working hours $4,856 - $4,856
75,868
kWh
02 2.7221: Lower temperature during the winter season and vice-versa $1,050 - $1,050
16,408
kWh
03 2.7314: Reduce ventilation air $2,819 - $2,819
44,047
kWh
TOTAL RECOMMENDED $8,725 - $8,725
136,323
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs