ITAC Assessment: LT8385
ITAC logo
ITAC Assessment: LT8385
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Centrifugal Pumps and Pump Services
NAICS 333996: Fluid Power Pump and Motor Manufacturing
SIC 3561: Pumps and Pumping Equipment
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area 35,783
ft2
Annual Production 70
units
Production Hrs. Annual 4,680
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $240,516 1,757,829
kWh
Electricity Demand $225,851 38,141
kW-mo/yr
Electricity Fees $5,717 -
Natural Gas $2,511 174
MMBtu
Fuel Oil #1 $7,616 215
MMBtu
Other Gas $1 60
MMBtu
Other Energy $7,616 215
MMBtu
Waste Disposal Costs
Water Usage $3,554 958
Tgal
Water Disposal $3,554 958
Tgal
Other Liquid (non-haz) $1 699
gal
TOTAL YEARLY COSTS $496,936
RECOMMENDED SAVINGS* $12,274 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 4.821: Pay bills on time to avoid late fees $6,415 - - - $6,415
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,025 $705 $1,025
12,963
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,834 $7,403 $4,170
43,688
kWh
$663
-
kW-mo/yr
-
TOTAL RECOMMENDED $12,274 $8,108 $5,195
56,650
kWh
$663
-
kW-mo/yr
$6,415
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs