Assessment Year | 2023 |
---|---|
Principal Product | Centrifugal Pumps and Pump Services |
NAICS | 333996: Fluid Power Pump and Motor Manufacturing |
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
35,783
ft2
|
Annual Production | 70
units
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $240,516 | 1,757,829 |
kWh
|
$0.14 | |
Electricity Demand | $225,851 | 38,141 |
kW-mo/yr
|
$5.92 | |
Electricity Fees | $5,717 | - |
|
- | |
Natural Gas | $2,511 | 174 |
MMBtu
|
$14.41 | |
Fuel Oil #1 | $7,616 | 215 |
MMBtu
|
$35.38 | |
Other Gas | $1 | 60 |
MMBtu
|
$0.017 | |
Other Energy | $7,616 | 215 |
MMBtu
|
$35.38 | |
Waste Disposal Costs | |||||
Water Usage | $3,554 | 958 |
Tgal
|
$3.71 | |
Water Disposal | $3,554 | 958 |
Tgal
|
$3.71 | |
Other Liquid (non-haz) | $1 | 699 |
gal
|
$0.001 | |
TOTAL YEARLY COSTS | $496,936 | ||||
RECOMMENDED SAVINGS* | $12,274 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 4.821: Pay bills on time to avoid late fees | $6,415 | - | - | - | $6,415 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,025 | $705 |
$1,025
12,963
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,834 | $7,403 |
$4,170
43,688
kWh
|
$663
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $12,274 | $8,108 |
$5,195
56,650
kWh
|
$663
-
kW-mo/yr
|
$6,415 | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs