ITAC Assessment: LT8380
ITAC logo
ITAC Assessment: LT8380
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Work Orders
NAICS 336510: Railroad Rolling Stock Manufacturing
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 138
Plant Area 150,000
ft2
Annual Production 750
units
Production Hrs. Annual 2,496
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $89,811 1,080,594
kWh
Electricity Demand $79,502 5,521
kW-mo/yr
Waste Disposal Costs
Water Usage $2,366 375
Tgal
Water Disposal $2,366 375
Tgal
TOTAL YEARLY COSTS $174,045
RECOMMENDED SAVINGS* $23,701 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $2,583 $2,922 $1,780
21,416
kWh
$865
-
kW-mo/yr
$(-62.1)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $916 $843 $706
8,498
kWh
$210
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,502 $255 $2,502
30,105
kWh
- -
04 4.652: Replace existing equipment with more suitable substitutes $17,700 $1,500 - - $17,700
TOTAL RECOMMENDED $23,701 $5,520 $4,988
60,019
kWh
$1,075
-
kW-mo/yr
$17,638
TOTAL IMPLEMENTED - - - - -