ITAC Assessment: LT8379
ITAC logo
ITAC Assessment: LT8379
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Oil & Gas Pressure Control Equipment
NAICS 333132: Oil and Gas Field Machinery and Equipment Manufacturing
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 158
Plant Area 1,132,560
ft2
Annual Production 73,535,756
lb
Production Hrs. Annual 6,864
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,151 3,727,975
kWh
Electricity Demand $151,312 10,145
kW-mo/yr
Electricity Fees $8,979 -
Natural Gas $102,978 6,532
MMBtu
Waste Disposal Costs
Water Usage $17,422 2,291
Tgal
TOTAL YEARLY COSTS $554,841
RECOMMENDED SAVINGS* $22,210 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,184 $17,100 $2,975
40,483
kWh
$1,209
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $844 $2,073 $496
6,745
kWh
$348
-
kW-mo/yr
-
03 2.6218: Turn off equipment when not in use $2,673 $1,193 $1,529
20,800
kWh
$1,163
-
kW-mo/yr
$(-18.8)
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $14,508 $5,600 $14,508
197,394
kWh
- -
TOTAL RECOMMENDED $22,210 $25,966 $19,508
265,421
kWh
$2,720
-
kW-mo/yr
$(-18.8)
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs