Assessment Year | 2022 |
---|---|
Principal Product | Metal Tubing |
NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
SIC | 3317: Steel Pipe and Tubes |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
170,000
ft2
|
Annual Production | 3,200
thousand feet
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $409,717 | 4,341,600 |
kWh
|
$0.094 | |
Electricity Demand | $86,844 | 10,904 |
kW-mo/yr
|
$7.96 | |
LPG | $1,115 | 36 |
MMBtu
|
$31.18 | |
Waste Disposal Costs | |||||
Water Usage | $9,950 | 1,786 |
Tgal
|
$5.57 | |
Water Disposal | $2,895 | 1,666 |
Tgal
|
$1.74 | |
TOTAL YEARLY COSTS | $510,520 | ||||
RECOMMENDED SAVINGS* | $73,965 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4131: Size electric motors for peak operating efficiency | $54,602 | - |
$43,912
465,317
kWh
|
$10,690
-
kW-mo/yr
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,106 | $26,500 |
$16,106
170,668
kWh
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $3,257 | $9,840 |
$2,619
27,756
kWh
|
$638
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $73,965 | $36,340 |
$62,637
663,740
kWh
|
$11,328
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs