ITAC Assessment: LT8363
ITAC logo
ITAC Assessment: LT8363
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Bread products
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $100
M
to 500
M
# of Employees 100
Plant Area 53,600
ft2
Annual Production 30,000,000
units
Production Hrs. Annual 7,500
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $436,000 5,004,300
kWh
Electricity Demand $124,619 8,801
kW-mo/yr
Natural Gas $27,810 2,189
MMBtu
LPG $620 20
MMBtu
Waste Disposal Costs
Water Usage $12,102 3,998
Tgal
Water Disposal $21,335 3,998
Tgal
TOTAL YEARLY COSTS $622,486
RECOMMENDED SAVINGS* $138,991 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $5,980 $10,022 - - $5,980 - - -
02 4.632: Change operating conditions $46,622 - - - - - $46,622 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $24,542 $2,945 $3,623
41,507
kWh
$20,919
-
kW-mo/yr
- - - -
04 3.1191: Change procedures / equipment / operating conditions $14,468 $15,975 - - - - - $14,468
05 2.7425: Clean or color roof to reduce solar load $22,308 $32,500 $18,400
211,000
kWh
$3,908
-
kW-mo/yr
- - - -
06 2.2441: Preheat boiler makeup water with waste process heat $23,817 $51,385 - - - $23,817
-
MMBtu
- -
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,254 - $1,016
11,633
kWh
$238
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $138,991 $112,827 $23,039
264,141
kWh
$25,065
-
kW-mo/yr
$5,980 $23,817
-
MMBtu
$46,622 $14,468
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs