ITAC Assessment: LT0136
ITAC logo
ITAC Assessment: LT0136
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product WOOD PARQUET FLOORING
NAICS
n/a
SIC 2426: Hardwood Dimension and Flooring Mills
Sales Range $1
M
to 5
M
# of Employees 60
Plant Area
n/a
Annual Production 1,250
thousand feet
Production Hrs. Annual 1,968
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,942 911,489
kWh
Natural Gas $24,697 5,610
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,164 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,084

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.5194: Redesign process $5,130 $720 - $5,130
-
MMBtu
02 2.7231: Use radiant heater for spot heating $950 $1,200 - $950
-
MMBtu
03 2.4133: Use most efficient type of electric motors $689 $1,755 $689
9,086
kWh
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,235 $246 $1,235
16,120
kWh
-
05 2.7111: Reduce illumination to minimum necessary levels $160 - $160
3,224
kWh
-
TOTAL RECOMMENDED $8,164 $3,921 $2,084
28,430
kWh
$6,080
-
MMBtu
TOTAL IMPLEMENTED $2,084 $2,001 $2,084
28,430
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs