| Assessment Year | 1988 |
|---|---|
| Principal Product | RUBBER ROLL COVERINGS |
| NAICS |
n/a
|
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 32 |
| Plant Area |
n/a
|
| Annual Production | 350,000,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $69,398 | 1,354,045 |
kWh
|
$0.051 |
| Natural Gas | $28,993 | 6,752 |
MMBtu
|
$4.29 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $4,247 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,235 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $124 | $200 | - |
$124
-
MMBtu
|
- | |
| 02 | 2.6218: Turn off equipment when not in use | $1,336 | - |
$1,336
33,411
kWh
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $564 | - |
$564
14,068
kWh
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $608 | $1,188 |
$608
12,896
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,164 | - |
$1,164
23,740
kWh
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $280 | $109 |
$311
6,448
kWh
|
- | $(-31.0) | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $171 | $372 |
$102
2,638
kWh
|
- | $69 | |
| TOTAL RECOMMENDED | $4,247 | $1,869 |
$4,085
93,201
kWh
|
$124
-
MMBtu
|
$38 | ||
| TOTAL IMPLEMENTED | $3,235 | $372 |
$3,166
73,857
kWh
|
- | $69 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs