ITAC Assessment: LT0109
ITAC logo
ITAC Assessment: LT0109
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product HARDWOOD LUBMER CHIPS
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 289
Plant Area
n/a
Annual Production 118,000
ton
Production Hrs. Annual 8,568
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,211,881 17,975,967
kWh
Wood $522,000 870,002
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $99,300 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $83,561

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $21,900 $20,000 - $21,900
-
MMBtu
-
02 2.1232: Keep boiler tubes clean $15,000 $7,000 - $15,000
-
MMBtu
-
03 2.2121: Increase amount of condensate returned $10,339 - $(-2,661.0)
(-63,892)
kWh
$11,800
-
MMBtu
$1,200
04 2.3212: Optimize plant power factor $36,350 $750 $36,350
-
kWh
- -
05 2.4133: Use most efficient type of electric motors $5,400 $12,150 $5,400
84,994
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $10,311 $15,000 $8,878
182,005
kWh
- $1,433
TOTAL RECOMMENDED $99,300 $54,900 $47,967
203,107
kWh
$48,700
-
MMBtu
$2,633
TOTAL IMPLEMENTED $83,561 $42,750 $45,228
182,005
kWh
$36,900
-
MMBtu
$1,433
Yearly Savings* Imp'd Cost* Electricity Usage Savings Wood Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs