| Assessment Year | 1987 |
|---|---|
| Principal Product | ROUGH LUMBER & PLYWOOD |
| NAICS |
n/a
|
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $10 M to 50M |
| # of Employees | 322 |
| Plant Area |
n/a
|
| Annual Production | 190,000
thousand feet
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,466,067 | 28,157,093 |
kWh
|
$0.052 |
| Natural Gas | $598,561 | 376,174 |
MMBtu
|
$1.59 |
| Wood | $649,000 | 1,118,000 |
MMBtu
|
$0.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $53,691 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $53,691 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $10,700 | $20,000 | - |
$10,700
-
MMBtu
|
|
| 02 | 2.2127: Flash condensate to produce lower pressure steam | $21,000 | $12,000 | - |
$21,000
-
MMBtu
|
|
| 03 | 2.2211: Use optimum temperature | $6,500 | $6,500 | - |
$6,500
-
MMBtu
|
|
| 04 | 2.2135: Repair and eliminate steam leaks | $671 | $275 | - |
$671
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,270 | $10,950 |
$4,270
68,875
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $280 | $83 |
$280
5,862
kWh
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $3,380 | $4,056 |
$3,380
79,719
kWh
|
- | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,890 | - |
$6,890
162,075
kWh
|
- | |
| TOTAL RECOMMENDED | $53,691 | $53,864 |
$14,820
316,531
kWh
|
$38,871
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $53,691 | $53,864 |
$14,820
316,531
kWh
|
$38,871
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs