| Assessment Year | 1987 |
|---|---|
| Principal Product | LUMBER |
| NAICS |
n/a
|
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $5 M to 10M |
| # of Employees | 78 |
| Plant Area |
n/a
|
| Annual Production | 29,000
thousand feet
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $229,317 | 3,898,007 |
kWh
|
$0.059 |
| Natural Gas | $1,989 | 415 |
MMBtu
|
$4.79 |
| Wood | $906,024 | 453,014 |
MMBtu
|
$2.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $648,343 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,258 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $25,500 | $2,500 | - |
$25,500
-
MMBtu
|
- | |
| 02 | 2.2422: Use waste heat from hot flue gases to generate steam | $609,085 | - |
$9,085
156,800
kWh
|
- | $600,000 | |
| 03 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $408 | $25,000 | - |
$408
-
MMBtu
|
- | |
| 04 | 2.2136: Install / repair insulation on steam lines | $1,610 | $5,000 | - |
$1,610
-
MMBtu
|
- | |
| 05 | 2.2122: Install / repair insulation on condensate lines | $5,720 | $3,458 | - |
$5,720
-
MMBtu
|
- | |
| 06 | 2.2135: Repair and eliminate steam leaks | $3,200 | $420 | - |
$3,200
-
MMBtu
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $2,820 | $6,471 |
$2,820
43,962
kWh
|
- | - | |
| TOTAL RECOMMENDED | $648,343 | $42,849 |
$11,905
200,762
kWh
|
$36,438
-
MMBtu
|
$600,000 | ||
| TOTAL IMPLEMENTED | $39,258 | $42,849 |
$2,820
43,962
kWh
|
$36,438
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs