ITAC Assessment: LT0046
ITAC logo
ITAC Assessment: LT0046
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product LIQUIFIED ANIMAL FAT
NAICS
n/a
SIC 2077: Animal and Marine Fats and Oils
Sales Range $1
M
to 5
M
# of Employees 18
Plant Area
n/a
Annual Production 2,570
ton
Production Hrs. Annual 2,750
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $5,899 94,080
kWh
Natural Gas $63,376 14,511
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,669 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,319

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $1,262 - - $1,862
-
MMBtu
$(-600.0)
02 2.2122: Install / repair insulation on condensate lines $350 $689 - $350
-
MMBtu
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $57 $65 $57
879
kWh
- -
TOTAL RECOMMENDED $1,669 $754 $57
879
kWh
$2,212
-
MMBtu
$(-600.0)
TOTAL IMPLEMENTED $1,319 $65 $57
879
kWh
$1,862
-
MMBtu
$(-600.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs