ITAC Assessment: LT0025
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product FORGED PIPE FITTINGS
NAICS
n/a
SIC 3462: Iron and Steel Forgings
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area
n/a
Annual Production 1,100,000
lb
Production Hrs. Annual 2,080
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,522 1,565,944
kWh
Natural Gas $75,769 17,201
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,356 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,356

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $154 $300 - $154
-
MMBtu
02 2.1131: Repair faulty insulation in furnaces, boilers, etc $537 $670 - $537
-
MMBtu
03 2.1135: Repair furnaces and oven doors so that they seal efficiently $6,134 $500 - $6,134
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $531 $400 $531
12,309
kWh
-
TOTAL RECOMMENDED $7,356 $1,870 $531
12,309
kWh
$6,825
-
MMBtu
TOTAL IMPLEMENTED $7,356 $1,870 $531
12,309
kWh
$6,825
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs