ITAC Assessment: LT0013
ITAC logo
ITAC Assessment: LT0013
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product HARDWOOD VENEER
NAICS
n/a
SIC 2435: Hardwood Veneer and Plywood
Sales Range $500
k
to 1
M
# of Employees 22
Plant Area
n/a
Annual Production 480
thousand feet
Production Hrs. Annual 2,080
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $11,243 157,093
kWh
Natural Gas $63,645 11,983
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,631 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,631

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $1,540 - $1,540
-
MMBtu
02 2.1131: Repair faulty insulation in furnaces, boilers, etc $425 $561 $425
-
MMBtu
03 2.2514: Cover open tanks $11,045 $3,631 $11,045
-
MMBtu
04 2.2136: Install / repair insulation on steam lines $127 $181 $127
-
MMBtu
05 2.6124: Establish equipment maintenance schedule $494 $50 $494
-
MMBtu
TOTAL RECOMMENDED $13,631 $4,423 $13,631
-
MMBtu
TOTAL IMPLEMENTED $13,631 $4,423 $13,631
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs