ITAC Assessment: LS2514
ITAC logo
ITAC Assessment: LS2514
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Processed Shrimp
NAICS 311710: Seafood Product Preparation and Packaging
SIC 2091: Canned and Cured Fish and Seafoods
Sales Range $1
M
to 5
M
# of Employees 8
Plant Area 55,000
ft2
Annual Production 2,000,000
lb
Production Hrs. Annual 2,940
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $69,638 397,781
kWh
Natural Gas $21,368 2,406
MMBtu
LPG $1,707 43
MMBtu
Waste Disposal Costs
Water Usage $4,782 9,794
Tgal
TOTAL YEARLY COSTS $97,495
RECOMMENDED SAVINGS* $62,605 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings Administrative Changes Savings Increase in Production Savings
01 2.4323: Use optimum size and capacity equipment $29,625 $52,000 - $2,185
-
MMBtu
- - $27,440
02 2.2443: Re-use or recycle hot or cold process exhaust air $3,979 $12,000 - $3,979
-
MMBtu
- - -
03 4.652: Replace existing equipment with more suitable substitutes $11,791 $45,000 $6,791
38,808
kWh
- - $5,000 -
04 2.1321: Replace fossil fuel equipment with electrical equipment $17,210 $96,366 $(-524.0)
(-2,995)
kWh
- $1,734
-
MMBtu
$16,000 -
TOTAL RECOMMENDED $62,605 $205,366 $6,267
35,813
kWh
$6,164
-
MMBtu
$1,734
-
MMBtu
$21,000 $27,440
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs