ITAC Assessment: LS2513
ITAC logo
ITAC Assessment: LS2513
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Processed Shrimp
NAICS 311710: Seafood Product Preparation and Packaging
SIC 2091: Canned and Cured Fish and Seafoods
Sales Range $500
k
to 1
M
# of Employees 12
Plant Area 22,183
ft2
Annual Production 770,000
lb
Production Hrs. Annual 3,650
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $101,697 492,366
kWh
Natural Gas $509 36
MMBtu
LPG $5,621 114
MMBtu
TOTAL YEARLY COSTS $107,827
RECOMMENDED SAVINGS* $69,647 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Personnel Changes Savings Administrative Changes Savings Primary Product Savings
01 3.5313: Increase amount of waste recovered for resale $12,200 - - - - - $12,200
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,376 $300 $1,376
6,646
kWh
- - - -
03 4.441: Install automatic packing equipment $36,000 $50,000 - - $36,000 - -
04 2.1321: Replace fossil fuel equipment with electrical equipment $20,071 $96,366 $(-1,550.0)
(-7,488)
kWh
$5,621
-
MMBtu
- $16,000 -
TOTAL RECOMMENDED $69,647 $146,666 $(-174.0)
(-842)
kWh
$5,621
-
MMBtu
$36,000 $16,000 $12,200
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs