ITAC Assessment: LS2512
ITAC logo
ITAC Assessment: LS2512
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Water Purification System
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3625: Relays and Industrial Controls
Sales Range $50
M
to 100
M
# of Employees 235
Plant Area 100,000
ft2
Annual Production 85
units
Production Hrs. Annual 6,500
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,987 1,389,200
kWh
Electricity Demand $150,890 10,039
kW-mo/yr
Natural Gas $61,275 7,363
MMBtu
LPG $4,803 97
MMBtu
TOTAL YEARLY COSTS $313,955
RECOMMENDED SAVINGS* $83,261 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Administrative Changes Savings Ancillary Material Cost Savings Increase in Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,432 $1,275 $891
12,730
kWh
$541
-
kW-mo/yr
- - - - -
02 4.322: Eliminate old stock and modify inventory control $16,150 $25,000 - - - - $9,750 $6,400 -
03 2.7425: Clean or color roof to reduce solar load $6,381 $25,002 $6,381
91,157
kWh
- - - - - -
04 2.1224: Replace boiler $31,301 $143,295 - - $5,051
-
MMBtu
- - - $26,250
05 2.1321: Replace fossil fuel equipment with electrical equipment $27,997 $144,549 $(-786.0)
(-11,232)
kWh
- - $4,783
-
MMBtu
$24,000 - -
TOTAL RECOMMENDED $83,261 $339,121 $6,486
92,655
kWh
$541
-
kW-mo/yr
$5,051
-
MMBtu
$4,783
-
MMBtu
$33,750 $6,400 $26,250
TOTAL IMPLEMENTED - - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs