Assessment Year | 2024 |
---|---|
Principal Product | Industrial Valves |
NAICS | 332911: Industrial Valve Manufacturing |
SIC | 3491: Industrial Valves |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
211,185
ft2
|
Annual Production | 6,200
pieces
|
Production Hrs. Annual | 5,616
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $371,048 | 3,375,023 |
kWh
|
$0.11 |
Electricity Demand | $10,093 | 3,001 |
kW-mo/yr
|
$3.36 |
Natural Gas | $11,648 | 2,142 |
MMBtu
|
$5.44 |
LPG | $10,467 | 208 |
MMBtu
|
$50.32 |
TOTAL YEARLY COSTS | $403,256 | |||
RECOMMENDED SAVINGS* | $27,361 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7211: Clean and maintain refrigerant condensers and towers | $7,922 | - |
$7,922
72,020
kWh
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,742 | $100 |
$2,742
24,928
kWh
|
- | |
03 | 2.7135: Install occupancy sensors | $6,194 | $300 |
$6,194
56,313
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $889 | $45 |
$889
8,083
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,614 | $6,975 |
$9,026
82,050
kWh
|
$588
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $27,361 | $7,420 |
$26,773
243,394
kWh
|
$588
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs