Assessment Year | 2024 |
---|---|
Principal Product | Lubricating Fluids |
NAICS | 324191: Petroleum Lubricating Oil and Grease Manufacturing |
SIC | 2992: Lubricating Oils and Greases |
Sales Range | $50 M to 100M |
# of Employees | 300 |
Plant Area |
619,542
ft2
|
Annual Production | 180,000,000
units
|
Production Hrs. Annual | 4,625
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,329,976 | 16,276,800 |
kWh
|
$0.082 |
Electricity Demand | $156,020 | 37,317 |
kW-mo/yr
|
$4.18 |
Natural Gas | $265,295 | 92,803 |
MMBtu
|
$2.86 |
TOTAL YEARLY COSTS | $1,751,291 | |||
RECOMMENDED SAVINGS* | $344,165 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $204,127 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7211: Clean and maintain refrigerant condensers and towers | $3,278 | - |
$3,278
39,976
kWh
|
- | - | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $11,023 | $50 |
$11,023
134,432
kWh
|
- | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,417 | $135 |
$1,417
17,279
kWh
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $44,207 | $25,301 |
$39,043
476,135
kWh
|
$5,164
-
kW-mo/yr
|
- | - | - | - | |
05 | 4.652: Replace existing equipment with more suitable substitutes | $155,225 | $550,000 |
$4,525
55,181
kWh
|
- | - | $148,000 | $2,700 | - | |
06 | 2.3192: Use fossil fuel powered generator during peak demand periods | $129,015 | $600,000 | - | - |
$(-7,660.0)
-
MMBtu
|
- | $1,675 | $135,000 | |
TOTAL RECOMMENDED | $344,165 | $1,175,486 |
$59,286
723,003
kWh
|
$5,164
-
kW-mo/yr
|
$(-7,660.0)
-
MMBtu
|
$148,000 | $4,375 | $135,000 | ||
TOTAL IMPLEMENTED | $204,127 | $575,436 |
$48,263
588,571
kWh
|
$5,164
-
kW-mo/yr
|
- | $148,000 | $2,700 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs