| Assessment Year | 2021 |
|---|---|
| Principal Product | Textile Bags and Canvas Mills |
| NAICS | 314910: Textile Bag and Canvas Mills |
| SIC | 2399: Fabricated Textile Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
280,000
ft2
|
| Annual Production | 500,000
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Louisiana |
| View Case Study | |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $83,370 | 868,500 |
kWh
|
$0.096 |
| Electricity Demand | $7,081 | 2,045 |
kW-mo/yr
|
$3.46 |
| Other Gas | $15,000 | 441 |
MMBtu
|
$34.01 |
| TOTAL YEARLY COSTS | $105,451 | |||
| RECOMMENDED SAVINGS* | $57,584 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,691 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $1,466 | $100 |
$1,466
15,271
kWh
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $455 | $50 |
$455
4,737
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,367 | $675 |
$5,367
55,913
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,725 | $9,408 |
$8,050
83,866
kWh
|
$1,675
-
kW-mo/yr
|
|
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $133 | $580 |
$133
1,381
kWh
|
- | |
| 06 | 2.9114: Use solar heat to make electricty | $40,438 | $646,020 |
$40,438
421,258
kWh
|
- | |
| TOTAL RECOMMENDED | $57,584 | $656,833 |
$55,909
582,426
kWh
|
$1,675
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $16,691 | $10,763 |
$15,016
156,431
kWh
|
$1,675
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs