ITAC Assessment: LS2102
ITAC logo
ITAC Assessment: LS2102
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Beer
NAICS 312120: Breweries
SIC 2082: Malt Beverages
Sales Range $1
M
to 5
M
# of Employees 13
Plant Area 12,000
ft2
Annual Production 3,000
bbl
Production Hrs. Annual 3,120
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,380 212,723
kWh
Electricity Demand $2,723 661
kW-mo/yr
Natural Gas $12,754 862
MMBtu
Waste Disposal Costs
Water Usage $5,671 1,116
Tgal
TOTAL YEARLY COSTS $35,528
RECOMMENDED SAVINGS* $51,473 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,065

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
01 2.8123: Pay utility bills on time $902 $25 - $902 - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,529 $270 $1,529
22,617
kWh
- - -
03 2.2414: Use waste heat from hot flue gases to preheat $6,357 $4,200 - - $6,357
-
MMBtu
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $51 $141 $51
748
kWh
- - -
05 4.441: Install automatic packing equipment $42,634 $120,000 - - - $42,634
TOTAL RECOMMENDED $51,473 $124,636 $1,580
23,365
kWh
$902 $6,357
-
MMBtu
$42,634
TOTAL IMPLEMENTED $45,065 $120,295 $1,529
22,617
kWh
$902 - $42,634
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs