| Assessment Year | 2019 |
|---|---|
| Principal Product | Rocket Propulsion Testing |
| NAICS | 336415: Guided Missile and Space Vehicle Propulsion Unit and Propulsion Unit Parts Manufacturing |
| SIC | 3724: Aircraft Engines and Engine Parts |
| Sales Range | less than $500 k |
| # of Employees | 25 |
| Plant Area |
57,500
ft2
|
| Annual Production | 1
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $546,851 | 6,835,641 |
kWh
|
$0.080 | |
| Waste Disposal Costs | |||||
| Other Liquid (non-haz) | $46,800 | 93,600 |
gal
|
$0.50 | |
| TOTAL YEARLY COSTS | $593,651 | ||||
| RECOMMENDED SAVINGS* | $426,033 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $145,792 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6212: Turn off equipment during breaks, reduce operating time | $3,210 | - |
$3,210
40,121
kWh
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $64,386 | $25,000 |
$64,386
804,825
kWh
|
- | |
| 03 | 2.7145: Install skylights | $22,426 | $12,600 |
$22,426
280,320
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $31,396 | $21,120 |
$31,396
392,448
kWh
|
- | |
| 05 | 3.5313: Increase amount of waste recovered for resale | $46,800 | $30,000 | - |
$46,800
-
gal
|
|
| 06 | 2.9114: Use solar heat to make electricty | $257,815 | $4,915,152 |
$257,815
3,222,690
kWh
|
- | |
| TOTAL RECOMMENDED | $426,033 | $5,003,872 |
$379,233
4,740,404
kWh
|
$46,800
-
gal
|
||
| TOTAL IMPLEMENTED | $145,792 | $76,120 |
$98,992
1,237,394
kWh
|
$46,800
-
gal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs