ITAC Assessment: LS1816
ITAC logo
ITAC Assessment: LS1816
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Wastewater/Sewage Treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $10
M
to 50
M
# of Employees 44
Plant Area 2,875,000
ft2
Annual Production 73,000,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,886,430 29,463,000
kWh
Natural Gas $34,875 5,472
MMBtu
TOTAL YEARLY COSTS $1,921,305
RECOMMENDED SAVINGS* $323,113 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $377

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7135: Install occupancy sensors $377 $68 $377
5,887
kWh
-
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,290 $265 $1,290
20,151
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $41,129 $25,545 $41,129
642,634
kWh
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $40,029 $66,000 $40,029
625,302
kWh
-
05 2.1336: Install equipment to utilize waste fuel $7,510 $13,000 - $7,510
-
MMBtu
06 2.4131: Size electric motors for peak operating efficiency $232,778 $428,000 $232,778
3,637,152
kWh
-
TOTAL RECOMMENDED $323,113 $532,878 $315,603
4,931,126
kWh
$7,510
-
MMBtu
TOTAL IMPLEMENTED $377 $68 $377
5,887
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs