ITAC Assessment: LS1806
ITAC logo
ITAC Assessment: LS1806
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Raw/Baked cookie dough
NAICS 311821: Cookie and Cracker Manufacturing
SIC 2045: Prepared Flour Mixes and Doughs
Sales Range $5
M
to 10
M
# of Employees 47
Plant Area 70,000
ft2
Annual Production 3,000,000
lb
Production Hrs. Annual 2,000
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $178,992 2,214,000
kWh
TOTAL YEARLY COSTS $178,992
RECOMMENDED SAVINGS* $9,532 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $168 $100 $168
2,080
kWh
02 2.6212: Turn off equipment during breaks, reduce operating time $11 $9 $11
138
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,834 $13,581 $7,834
96,960
kWh
04 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating $1,519 $6,300 $1,519
18,796
kWh
TOTAL RECOMMENDED $9,532 $19,990 $9,532
117,974
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs