ITAC Assessment: LS1723
ITAC logo
ITAC Assessment: LS1723
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Elementary and Secondary Schools
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range less than $500
k
# of Employees 110
Plant Area 105,320
ft2
Annual Production 1
units
Production Hrs. Annual 4,800
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,263 886,938
kWh
Electricity Demand $12,904 3,132
kW-mo/yr
TOTAL YEARLY COSTS $116,167
RECOMMENDED SAVINGS* $72,004 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,734

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7211: Clean and maintain refrigerant condensers and towers $12,310 - $12,310
106,119
kWh
-
02 2.7224: Reduce space conditioning during non-working hours $3,341 - $3,341
28,805
kWh
-
03 2.6218: Turn off equipment when not in use $251 - $251
2,160
kWh
-
04 2.7135: Install occupancy sensors $817 $350 $817
7,043
kWh
-
05 2.7423: Reduce heat gain by window tinting $2,045 $2,688 $2,045
17,632
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $9,787 $15,377 $7,912
68,210
kWh
$1,875
-
kW-mo/yr
07 2.9114: Use solar heat to make electricty $43,453 $429,000 $43,453
374,595
kWh
-
TOTAL RECOMMENDED $72,004 $447,415 $70,129
604,564
kWh
$1,875
-
kW-mo/yr
TOTAL IMPLEMENTED $27,734 $18,065 $25,859
222,926
kWh
$1,875
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs