Assessment Year | 2005 |
---|---|
Principal Product | aerospace parts |
NAICS | 336419: Other Guided Missile and Space Vehicle Parts and Auxiliary Equipment Manufacturing |
SIC | 3769: Guided Missile Space Vehicle Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
46,500
ft2
|
Annual Production | 150
pieces
|
Production Hrs. Annual | 5,066
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $196,875 | 1,816,509 |
kWh
|
$0.11 |
Electricity Demand | $24,705 | 4,572 |
kW-mo/yr
|
$5.40 |
Electricity Fees | $12,489 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,714,972 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,264,972 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,202 | $500 |
$1,074
9,526
kWh
|
$128
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,058 | $1,000 |
$1,839
16,302
kWh
|
$219
-
kW-mo/yr
|
- | |
03 | 2.4239: Eliminate or reduce compressed air usage | $3,712 | $200 |
$3,288
29,148
kWh
|
$424
-
kW-mo/yr
|
- | |
04 | 4.132: Purchase new equipment to reduce material use / cost | $450,000 | $15,000 | - | - | $450,000 | |
05 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,258,000 | $1,250,000 | - | - | $1,258,000 | |
TOTAL RECOMMENDED | $1,714,972 | $1,266,700 |
$6,201
54,976
kWh
|
$771
-
kW-mo/yr
|
$1,708,000 | ||
TOTAL IMPLEMENTED | $1,264,972 | $1,251,700 |
$6,201
54,976
kWh
|
$771
-
kW-mo/yr
|
$1,258,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs