| Assessment Year | 2005 |
|---|---|
| Principal Product | potted plants |
| NAICS | 111422: Floriculture Production |
| SIC | 181: |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
1,000,000
ft2
|
| Annual Production | 6,000,000
pieces
|
| Production Hrs. Annual | 2,650
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $144,997 | 2,128,640 |
kWh
|
$0.068 |
| Electricity Demand | $36,593 | 5,846 |
kW-mo/yr
|
$6.26 |
| Electricity Fees | $528 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $81,413 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $820 | $6,493 |
$739
10,843
kWh
|
$81
-
kW-mo/yr
|
- | - | |
| 02 | 2.2511: Insulate bare equipment | $11,036 | $21,600 | - | - |
$11,036
-
MMBtu
|
- | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $3,133 | $200 |
$2,830
43,417
kWh
|
$303
-
kW-mo/yr
|
- | - | |
| 04 | 2.9114: Use solar heat to make electricty | $7,424 | $200,000 |
$7,424
113,900
kWh
|
- | - | - | |
| 05 | 4.652: Replace existing equipment with more suitable substitutes | $5,000 | $9,000 | - | - | - | $5,000 | |
| 06 | 4.515: Install shelves / racks to utilize unused space | $54,000 | $332,000 | - | - | - | $54,000 | |
| TOTAL RECOMMENDED | $81,413 | $569,293 |
$10,993
168,160
kWh
|
$384
-
kW-mo/yr
|
$11,036
-
MMBtu
|
$59,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs