ITAC Assessment: LM0075
ITAC logo
ITAC Assessment: LM0075
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Carpet Padding
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 160,000
ft2
Annual Production 332,371
thousand feet
Production Hrs. Annual 4,160
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $430,528 4,183,233
kWh
Electricity Demand $172,994 13,860
kW-mo/yr
Electricity Fees $8,561 -
Natural Gas $117,853 18,376
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $176,464 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $157,485

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $757 $175 $560
5,407
kWh
$197
-
kW-mo/yr
- -
02 2.4133: Use most efficient type of electric motors $1,356 $1,854 $1,145
9,161
kWh
$211
-
kW-mo/yr
- -
03 2.4131: Size electric motors for peak operating efficiency $552 $779 $409
3,951
kWh
$143
-
kW-mo/yr
- -
04 4.611: Begin a practice of predictive / preventative maintenance $156,419 $6,500 $5,411
52,312
kWh
- - $151,008
05 4.625: Develop standard operating procedures $14,640 $6,500 - - - $14,640
06 2.2511: Insulate bare equipment $309 $101 - - $309
-
MMBtu
-
07 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $2,431 $470 $1,885
18,231
kWh
$546
-
kW-mo/yr
- -
TOTAL RECOMMENDED $176,464 $16,379 $9,410
89,062
kWh
$1,097
-
kW-mo/yr
$309
-
MMBtu
$165,648
TOTAL IMPLEMENTED $157,485 $6,776 $5,971
57,719
kWh
$197
-
kW-mo/yr
$309
-
MMBtu
$151,008
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs