Assessment Year | 2004 |
---|---|
Principal Product | Tissue Paper and Absorbent Pads |
NAICS | 322121: Paper (except Newsprint) Mills |
SIC | 2621: Paper Mills |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
165,000
ft2
|
Annual Production | 14,000
ton
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $983,789 | 10,153,972 |
kWh
|
$0.097 |
Electricity Demand | $76,163 | 4,896 |
kW-mo/yr
|
$15.56 |
Electricity Fees | $162,946 | - |
|
- |
Natural Gas | $785,743 | 148,801 |
MMBtu
|
$5.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $520,559 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $379,434 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $8,308 | $15,300 |
$5,393
52,580
kWh
|
$2,915
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,630 | $6,666 |
$9,340
91,073
kWh
|
$2,290
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,974 | $410 |
$1,731
16,884
kWh
|
$243
-
kW-mo/yr
|
- | - | - | |
04 | 2.4239: Eliminate or reduce compressed air usage | $2,428 | $900 |
$2,130
20,800
kWh
|
$298
-
kW-mo/yr
|
- | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $417 | $15 |
$294
2,870
kWh
|
$123
-
kW-mo/yr
|
- | - | - | |
06 | 2.2136: Install / repair insulation on steam lines | $1,600 | $210 | - | - |
$1,600
-
MMBtu
|
- | - | |
07 | 2.2135: Repair and eliminate steam leaks | $4,998 | $108 | - | - |
$4,998
-
MMBtu
|
- | - | |
08 | 2.4133: Use most efficient type of electric motors | $1,274 | $835 |
$1,118
10,987
kWh
|
$156
-
kW-mo/yr
|
- | - | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,301 | $2,241 |
$2,019
19,685
kWh
|
$282
-
kW-mo/yr
|
- | - | - | |
10 | 2.4131: Size electric motors for peak operating efficiency | $6,358 | $10,398 |
$6,271
61,144
kWh
|
$87
-
kW-mo/yr
|
- | - | - | |
11 | 2.4313: Provide proper maintenance of motor driven equipment | $1,588 | $18 |
$1,390
13,550
kWh
|
$198
-
kW-mo/yr
|
- | - | - | |
12 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $170,219 | - | - | - | - | - | $170,219 | |
13 | 4.611: Begin a practice of predictive / preventative maintenance | $16,000 | $5,000 | - | - | - | $(-80,000.0) | $96,000 | |
14 | 4.444: Install system to collect scrap | $118,125 | $68,000 | - | - | - | $118,125 | - | |
15 | 4.426: Modify workload | $7,000 | $1,000 | - | - | - | $7,000 | - | |
16 | 4.625: Develop standard operating procedures | $86,625 | $14,470 | - | - | - | $86,625 | - | |
17 | 4.625: Develop standard operating procedures | $79,714 | $5,400 |
$10,414
101,540
kWh
|
- | - | $69,300 | - | |
TOTAL RECOMMENDED | $520,559 | $130,971 |
$40,100
391,113
kWh
|
$6,592
-
kW-mo/yr
|
$6,598
-
MMBtu
|
$201,050 | $266,219 | ||
TOTAL IMPLEMENTED | $379,434 | $56,971 |
$40,100
391,113
kWh
|
$6,592
-
kW-mo/yr
|
$6,598
-
MMBtu
|
$155,925 | $170,219 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs