ITAC Assessment: GT0280
ITAC logo
ITAC Assessment: GT0280
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product SYNTHETIC CARPET YARN
NAICS
n/a
SIC 2281: Yarn Spinning Mills
Sales Range $10
M
to 50
M
# of Employees 425
Plant Area
n/a
Annual Production 30,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $878,089 19,708,969
kWh
Natural Gas $256,994 58,204
MMBtu
Wood $102,019 219,343
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $164,839 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $130,034

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Wood Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $13,393 $700 - $13,393
-
MMBtu
-
02 3.6123: Burn wood by-products for heat $100,081 $6,200 - $133,007
-
MMBtu
$(-32,926.0)
-
MMBtu
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $9,064 $16,300 $9,064
203,400
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $18,846 $55,650 $18,846
422,919
kWh
- -
05 2.4133: Use most efficient type of electric motors $7,496 $5,921 $7,496
168,230
kWh
- -
06 2.2441: Preheat boiler makeup water with waste process heat $15,959 $35,750 - $3,784
-
MMBtu
$12,175
-
MMBtu
TOTAL RECOMMENDED $164,839 $120,521 $35,406
794,549
kWh
$150,184
-
MMBtu
$(-20,751.0)
-
MMBtu
TOTAL IMPLEMENTED $130,034 $29,121 $16,560
371,630
kWh
$146,400
-
MMBtu
$(-32,926.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Wood Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs