| Assessment Year | 2001 |
|---|---|
| Principal Product | thermal processing |
| NAICS |
n/a
|
| SIC | 3398: Metal Heat Treating |
| Sales Range | $10 M to 50M |
| # of Employees | 92 |
| Plant Area |
50,000
ft2
|
| Annual Production | 32,500,000
lb
|
| Production Hrs. Annual | 3,744
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $218,006 | 3,824,586 |
kWh
|
$0.057 |
| Electricity Demand | $73,486 | 8,892 |
kW-mo/yr
|
$8.26 |
| Electricity Fees | $135,848 | - |
|
- |
| Natural Gas | $160,969 | 26,224 |
MMBtu
|
$6.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $305,570 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $205,399 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,625 | $869 |
$1,387
20,043
kWh
|
$238
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,709 | - |
$2,275
32,886
kWh
|
$434
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $81,101 | $150,000 | - | - |
$81,101
-
MMBtu
|
- | - | |
| 04 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,792 | $11,800 | - | - | - | - | $4,792 | |
| 05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,575 | $300 | - | - | - | - | $1,575 | |
| 06 | 4.426: Modify workload | $201,115 | $1,000 | - | - | - | $201,115 | - | |
| 07 | 4.426: Modify workload | $12,653 | $1,199 | - | - | - | $12,653 | - | |
| TOTAL RECOMMENDED | $305,570 | $165,168 |
$3,662
52,929
kWh
|
$672
-
kW-mo/yr
|
$81,101
-
MMBtu
|
$213,768 | $6,367 | ||
| TOTAL IMPLEMENTED | $205,399 | $1,300 |
$2,275
32,886
kWh
|
$434
-
kW-mo/yr
|
- | $201,115 | $1,575 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs