Assessment Year | 2003 |
---|---|
Principal Product | Fireplace Units |
NAICS | 333414: Heating Equipment (except Warm Air Furnaces) Manufacturing |
SIC | 3433: Heating Equipment, Except Electric and Warm Air Furnaces |
Sales Range | $10 M to 50M |
# of Employees | 220 |
Plant Area |
200,000
ft2
|
Annual Production | 30,000
pieces
|
Production Hrs. Annual | 4,400
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $384,269 | 3,249,469 |
kWh
|
$0.12 |
Electricity Demand | $103,113 | 8,760 |
kW-mo/yr
|
$11.77 |
Electricity Fees | $55,817 | - |
|
- |
Natural Gas | $70,469 | 13,330 |
MMBtu
|
$5.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $718,319 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $714,483 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,003 | $6,290 |
$2,280
17,908
kWh
|
$723
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $5,246 | - |
$4,182
28,194
kWh
|
$1,064
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $711 | $724 |
$540
4,245
kWh
|
$171
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $415 | $219 |
$315
2,473
kWh
|
$100
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,369 | $410 |
$5,987
47,036
kWh
|
$1,902
-
kW-mo/yr
|
- | $(-520.0) | - | - | |
06 | 2.4234: Cool compressor air intake with heat exchanger | $3,170 | $1,950 |
$2,406
18,900
kWh
|
$764
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.1116: Improve combustion control capability | $666 | $750 | - | - |
$666
-
MMBtu
|
- | - | - | |
08 | 2.7229: Air condition only space necessary | $17,255 | - |
$10,948
55,601
kWh
|
$6,307
-
kW-mo/yr
|
- | - | - | - | |
09 | 4.431: Train operators for maximum operating efficiency | $52,500 | $19,910 | - | - | - | - | - | $52,500 | |
10 | 4.431: Train operators for maximum operating efficiency | $105,000 | $17,500 | - | - | - | - | - | $105,000 | |
11 | 4.611: Begin a practice of predictive / preventative maintenance | $17,820 | $3,000 | - | - | - | $(-82,800.0) | - | $100,620 | |
12 | 4.131: Modify process to reduce material use/cost | $505,164 | - | - | - | - | - | $505,164 | - | |
TOTAL RECOMMENDED | $718,319 | $50,753 |
$26,658
174,357
kWh
|
$11,031
-
kW-mo/yr
|
$666
-
MMBtu
|
$(-83,320.0) | $505,164 | $258,120 | ||
TOTAL IMPLEMENTED | $714,483 | $48,053 |
$24,252
155,457
kWh
|
$10,267
-
kW-mo/yr
|
- | $(-83,320.0) | $505,164 | $258,120 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs