Assessment Year | 2003 |
---|---|
Principal Product | Motorcycle Parts |
NAICS | 336991: Motorcycle, Bicycle, and Parts Manufacturing |
SIC | 3751: Motorcycles, Bicycles, and Parts |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
95,000
ft2
|
Annual Production | 700,000
pieces
|
Production Hrs. Annual | 5,304
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $332,769 | 2,826,969 |
kWh
|
$0.12 |
Electricity Demand | $125,480 | 9,252 |
kW-mo/yr
|
$13.56 |
Electricity Fees | $34,272 | - |
|
- |
Natural Gas | $59,672 | 12,081 |
MMBtu
|
$4.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $254,030 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $179,652 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $37,718 | $300 | - | - | - | - | $(-34,650.0) | $72,368 | |
02 | 2.7232: Replace existing hvac unit with high efficiency model | $7,782 | $12,000 |
$5,559
34,000
kWh
|
$2,223
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2514: Cover open tanks | $1,410 | $175 | - | - |
$1,410
-
MMBtu
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,131 | $100 |
$3,109
24,930
kWh
|
$802
-
kW-mo/yr
|
- | - | $(-780.0) | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $12,820 | $650 |
$10,192
81,726
kWh
|
$2,628
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7144: Install spectral reflectors / delamp | $1,881 | - |
$1,612
11,138
kWh
|
$269
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,819 | $12,615 |
$6,216
49,836
kWh
|
$1,603
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $8,917 | $1,000 |
$7,089
56,837
kWh
|
$1,828
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7124: Make a practice of turning off lights when not needed | $1,049 | $100 |
$834
6,683
kWh
|
$215
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.4133: Use most efficient type of electric motors | $8,416 | $14,328 |
$6,691
53,650
kWh
|
$1,725
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,936 | $2,088 |
$3,120
24,960
kWh
|
$816
-
kW-mo/yr
|
- | - | - | - | |
12 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,651 | $11,000 | - | - | - |
$8,926
-
lb
|
$(-1,275.0) | - | |
13 | 3.5217: Reuse / recycle/ sell paper products | $1,200 | $75 | - | - | - | - | - | $1,200 | |
14 | 4.652: Replace existing equipment with more suitable substitutes | $37,800 | $20,000 | - | - | - | - | - | $37,800 | |
15 | 4.431: Train operators for maximum operating efficiency | $112,500 | $8,120 | - | - | - | - | - | $112,500 | |
TOTAL RECOMMENDED | $254,030 | $82,551 |
$44,422
343,760
kWh
|
$12,109
-
kW-mo/yr
|
$1,410
-
MMBtu
|
$8,926
-
lb
|
$(-36,705.0) | $223,868 | ||
TOTAL IMPLEMENTED | $179,652 | $45,386 |
$23,946
191,949
kWh
|
$6,186
-
kW-mo/yr
|
- | - | $(-780.0) | $150,300 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs