Assessment Year | 2003 |
---|---|
Principal Product | transformers |
NAICS | 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing |
SIC | 3677: Electronic Coils, Transformers, and Other Inductors |
Sales Range | $1 M to 5M |
# of Employees | 80 |
Plant Area |
28,000
ft2
|
Annual Production | 14,400
pieces
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $65,486 | 547,440 |
kWh
|
$0.12 |
Electricity Demand | $15,520 | 1,884 |
kW-mo/yr
|
$8.24 |
Electricity Fees | $5,322 | - |
|
- |
Natural Gas | $2,779 | 431 |
MMBtu
|
$6.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $108,064 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7144: Install spectral reflectors / delamp | $1,027 | - |
$793
6,120
kWh
|
$234
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,855 | $6,210 |
$2,205
17,010
kWh
|
$650
-
kW-mo/yr
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $34 | - |
$26
197
kWh
|
$8
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,585 | $3,275 |
$1,238
9,553
kWh
|
$347
-
kW-mo/yr
|
- | - | |
05 | 4.432: Cross-train personnel to avoid lost time | $64,652 | $4,768 | - | - | $64,652 | - | |
06 | 4.122: Develop standard procedures to improve internal yields | $37,911 | $24,550 | - | - | - | $37,911 | |
TOTAL RECOMMENDED | $108,064 | $38,803 |
$4,262
32,880
kWh
|
$1,239
-
kW-mo/yr
|
$64,652 | $37,911 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs