Assessment Year | 2003 |
---|---|
Principal Product | fabrication of dies, jigs, and tools |
NAICS | 333514: Special Die and Tool, Die Set, Jig, and Fixture Manufacturing |
SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
42,500
ft2
|
Annual Production | 1,162
pieces
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $144,796 | 1,191,900 |
kWh
|
$0.12 |
Electricity Demand | $34,639 | 7,848 |
kW-mo/yr
|
$4.41 |
Electricity Fees | $4,973 | - |
|
- |
Natural Gas | $1,307 | 164 |
MMBtu
|
$7.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $590,592 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $584 | $767 |
$482
4,033
kWh
|
$102
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,644 | $500 |
$8,046
67,260
kWh
|
$1,286
-
kW-mo/yr
|
$(-688.0) | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,526 | - |
$2,239
18,031
kWh
|
$287
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,935 | $2,250 |
$2,530
21,150
kWh
|
$405
-
kW-mo/yr
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $14,728 | $1,000 |
$14,728
113,400
kWh
|
- | - | - | |
06 | 4.431: Train operators for maximum operating efficiency | $198,375 | $32,670 | - | - | $198,375 | - | |
07 | 4.731: Advertise product or service | $242,800 | $2,000 | - | - | - | $242,800 | |
08 | 4.625: Develop standard operating procedures | $120,000 | $7,997 | - | - | - | $120,000 | |
TOTAL RECOMMENDED | $590,592 | $47,184 |
$28,025
223,874
kWh
|
$2,080
-
kW-mo/yr
|
$197,687 | $362,800 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs