ITAC Assessment: LM0048
ITAC logo
ITAC Assessment: LM0048
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product asphalt composite roofing shingles
NAICS 324122: Asphalt Shingle and Coating Materials Manufacturing
SIC 2952: Asphalt Felts and Coatings
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 125,000
ft2
Annual Production 132,000,000
pieces
Production Hrs. Annual 7,440
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $679,366 6,269,238
kWh
Electricity Demand $171,979 12,996
kW-mo/yr
Electricity Fees $49,690 -
Natural Gas $1,581,309 184,310
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $953,119 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $843,354

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
01 2.7124: Make a practice of turning off lights when not needed $3,065 - $2,553
22,570
kWh
$512
-
kW-mo/yr
- - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,111 $4,650 $6,743
49,945
kWh
$368
-
kW-mo/yr
- - - - -
03 2.4133: Use most efficient type of electric motors $1,650 $951 $1,374
12,150
kWh
$276
-
kW-mo/yr
- - - - -
04 2.4131: Size electric motors for peak operating efficiency $2,317 $3,200 $1,930
17,063
kWh
$387
-
kW-mo/yr
- - - - -
05 3.4115: Recover and reuse cooling water $16,200 $1,000 - - $16,200
-
Tgal
- - - -
06 4.625: Develop standard operating procedures $36,400 $14,567 - - - - - - $36,400
07 4.625: Develop standard operating procedures $25,093 $15,842 - - - - - $25,093 -
08 4.611: Begin a practice of predictive / preventative maintenance $105,000 $40,872 - - - $105,000 - - -
09 4.111: Add equipment/ operators to reduce production bottleneck $672,000 $100,000 - - - - - - $672,000
10 4.514: Re-arrange equipment layout to reduce handling costs $82,232 $25,000 - - - $82,232 - - -
11 4.132: Purchase new equipment to reduce material use / cost $1,700 $2,300 - - - - $1,700 - -
12 2.8114: Change rate schedules or other changes in utility service $351 - - - - - $351 - -
TOTAL RECOMMENDED $953,119 $208,382 $12,600
101,728
kWh
$1,543
-
kW-mo/yr
$16,200
-
Tgal
$187,232 $2,051 $25,093 $708,400
TOTAL IMPLEMENTED $843,354 $165,210 $10,047
79,158
kWh
$1,031
-
kW-mo/yr
$16,200
-
Tgal
$82,232 $351 $25,093 $708,400
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs