Assessment Year | 2002 |
---|---|
Principal Product | corrugated packaging |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
200,000
ft2
|
Annual Production | 1,200
thousand feet
|
Production Hrs. Annual | 5,976
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $410,612 | 4,501,264 |
kWh
|
$0.091 |
Electricity Demand | $130,655 | 11,580 |
kW-mo/yr
|
$11.28 |
Electricity Fees | $(-24,308.0) | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,064,829 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $324,187 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $604 | $350 |
$890
8,025
kWh
|
$214
-
kW-mo/yr
|
$(-500.0) | - | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $1,833 | $100 |
$1,480
13,341
kWh
|
$353
-
kW-mo/yr
|
- | - | - | |
03 | 2.4322: Use or replace with energy efficient substitutes | $6,250 | $1,000 |
$5,045
45,473
kWh
|
$1,205
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $122,392 | $68,248 |
$102,031
885,464
kWh
|
$20,361
-
kW-mo/yr
|
- | - | - | |
05 | 4.111: Add equipment/ operators to reduce production bottleneck | $612,000 | $1,100,000 | - | - | - | - | $612,000 | |
06 | 4.431: Train operators for maximum operating efficiency | $93,750 | $24,000 | - | - | - | $93,750 | - | |
07 | 4.321: Optimize production lot sizes and inventories | $228,000 | $1,000 | - | - | - | $228,000 | - | |
TOTAL RECOMMENDED | $1,064,829 | $1,194,698 |
$109,446
952,303
kWh
|
$22,133
-
kW-mo/yr
|
$(-500.0) | $321,750 | $612,000 | ||
TOTAL IMPLEMENTED | $324,187 | $25,450 |
$2,370
21,366
kWh
|
$567
-
kW-mo/yr
|
$(-500.0) | $321,750 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs