| Assessment Year | 2002 |
|---|---|
| Principal Product | plastic film |
| NAICS |
n/a
|
| SIC | 3081: Unsupported Plastics Film and Sheet |
| Sales Range | $50 M to 100M |
| # of Employees | 185 |
| Plant Area |
122,000
ft2
|
| Annual Production | 75,000,000
lb
|
| Production Hrs. Annual | 8,520
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,749,487 | 25,802,712 |
kWh
|
$0.068 |
| Electricity Demand | $447,343 | 43,284 |
kW-mo/yr
|
$10.34 |
| Electricity Fees | $110,501 | - |
|
- |
| Natural Gas | $750 | 67 |
MMBtu
|
$11.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $43,199 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,562 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7144: Install spectral reflectors / delamp | $20,645 | $300 |
$18,072
183,434
kWh
|
$2,573
-
kW-mo/yr
|
- | |
| 02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $6,353 | $1,480 |
$4,266
43,297
kWh
|
$2,087
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,937 | $200 |
$4,113
41,758
kWh
|
$604
-
kW-mo/yr
|
$(-780.0) | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,911 | - |
$3,411
34,623
kWh
|
$500
-
kW-mo/yr
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $2,006 | $2,640 |
$1,756
17,823
kWh
|
$250
-
kW-mo/yr
|
- | |
| 06 | 2.2515: Use optimum thickness insulation | $6,347 | $900 |
$5,527
56,097
kWh
|
$820
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $43,199 | $5,520 |
$37,145
377,032
kWh
|
$6,834
-
kW-mo/yr
|
$(-780.0) | ||
| TOTAL IMPLEMENTED | $26,562 | $2,940 |
$23,239
235,880
kWh
|
$3,323
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs