| Assessment Year | 2001 |
|---|---|
| Principal Product | stamped steel fasteners |
| NAICS |
n/a
|
| SIC | 3469: Metal Stampings, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
250,000
ft2
|
| Annual Production | 25,000,000
lb
|
| Production Hrs. Annual | 5,904
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $431,405 | 6,884,012 |
kWh
|
$0.063 |
| Electricity Demand | $185,141 | 28,632 |
kW-mo/yr
|
$6.47 |
| Electricity Fees | $90,002 | - |
|
- |
| Natural Gas | $638,392 | 113,803 |
MMBtu
|
$5.61 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,905,125 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,826,311 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $9,494 | $2,500 |
$8,095
75,976
kWh
|
$1,399
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $50,600 | $60,000 | - | - |
$50,600
-
MMBtu
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,311 | $3,335 |
$3,677
34,508
kWh
|
$634
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $18,720 | $15,300 | n/a | - | - | - | - | $18,720 |
| 05 | 4.625: Develop standard operating procedures | $1,482,000 | $5,000 | - | - | - | - | $1,482,000 | |
| 06 | 4.625: Develop standard operating procedures | $340,000 | $310,000 | - | - | - | $340,000 | - | |
| TOTAL RECOMMENDED | $1,905,125 | $396,135 |
$11,772
110,484
kWh
|
$2,033
-
kW-mo/yr
|
$50,600
-
MMBtu
|
$340,000 | $1,500,720 | ||
| TOTAL IMPLEMENTED | $1,826,311 | $318,335 |
$3,677
34,508
kWh
|
$634
-
kW-mo/yr
|
- | $340,000 | $1,482,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs