ITAC Assessment: LM0011
ITAC logo
ITAC Assessment: LM0011
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product tubes
NAICS
n/a
SIC 3400:
Sales Range $50
M
to 100
M
# of Employees 75
Plant Area 265,800
ft2
Annual Production 120,000
ton
Production Hrs. Annual 2,522
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $345,082 6,032,618
kWh
Electricity Demand $439,046 132,900
kW-mo/yr
Electricity Fees $29,009 -
Natural Gas $1,898 169
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $414,318 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $407,997

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Primary Product Savings Increase in Production Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,705 $250 $3,209
28,278
kWh
$1,276
-
kW-mo/yr
- $(-780.0) - -
02 2.4321: Upgrade obsolete equipment $804 $855 $573
5,023
kWh
$231
-
kW-mo/yr
- - - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $94,292 $450 - $31,422
-
kW-mo/yr
$43,983 $(-57,200.0) $76,087 -
04 2.7232: Replace existing hvac unit with high efficiency model $5,517 $12,000 $3,963
28,600
kWh
$1,554
-
kW-mo/yr
- - - -
05 4.611: Begin a practice of predictive / preventative maintenance $310,000 $1,000 - - - $(-40,000.0) - $350,000
TOTAL RECOMMENDED $414,318 $14,555 $7,745
61,901
kWh
$34,483
-
kW-mo/yr
$43,983 $(-97,980.0) $76,087 $350,000
TOTAL IMPLEMENTED $407,997 $1,700 $3,209
28,278
kWh
$32,698
-
kW-mo/yr
$43,983 $(-97,980.0) $76,087 $350,000
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs