Assessment Year | 2001 |
---|---|
Principal Product | tubes |
NAICS |
n/a
|
SIC | 3400: |
Sales Range | $50 M to 100M |
# of Employees | 75 |
Plant Area |
265,800
ft2
|
Annual Production | 120,000
ton
|
Production Hrs. Annual | 2,522
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $345,082 | 6,032,618 |
kWh
|
$0.057 |
Electricity Demand | $439,046 | 132,900 |
kW-mo/yr
|
$3.30 |
Electricity Fees | $29,009 | - |
|
- |
Natural Gas | $1,898 | 169 |
MMBtu
|
$11.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $414,318 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $407,997 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,705 | $250 |
$3,209
28,278
kWh
|
$1,276
-
kW-mo/yr
|
- | $(-780.0) | - | - | |
02 | 2.4321: Upgrade obsolete equipment | $804 | $855 |
$573
5,023
kWh
|
$231
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $94,292 | $450 | - |
$31,422
-
kW-mo/yr
|
$43,983 | $(-57,200.0) | $76,087 | - | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $5,517 | $12,000 |
$3,963
28,600
kWh
|
$1,554
-
kW-mo/yr
|
- | - | - | - | |
05 | 4.611: Begin a practice of predictive / preventative maintenance | $310,000 | $1,000 | - | - | - | $(-40,000.0) | - | $350,000 | |
TOTAL RECOMMENDED | $414,318 | $14,555 |
$7,745
61,901
kWh
|
$34,483
-
kW-mo/yr
|
$43,983 | $(-97,980.0) | $76,087 | $350,000 | ||
TOTAL IMPLEMENTED | $407,997 | $1,700 |
$3,209
28,278
kWh
|
$32,698
-
kW-mo/yr
|
$43,983 | $(-97,980.0) | $76,087 | $350,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs