| Assessment Year | 2001 |
|---|---|
| Principal Product | electronic chasis |
| NAICS |
n/a
|
| SIC | 3423: Hand and Edge Tools, Except Machine Tools and Handsaws |
| Sales Range | $1 M to 5M |
| # of Employees | 42 |
| Plant Area |
39,000
ft2
|
| Annual Production | 10,000
pieces
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $31,673 | 504,040 |
kWh
|
$0.063 |
| Electricity Demand | $39,620 | 3,924 |
kW-mo/yr
|
$10.10 |
| Electricity Fees | $12,097 | - |
|
- |
| Natural Gas | $2,700 | 275 |
MMBtu
|
$9.82 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $310,624 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $49,013 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7145: Install skylights | $8,789 | $8,500 |
$4,301
61,880
kWh
|
$4,488
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,547 | $725 |
$2,748
39,536
kWh
|
$2,359
-
kW-mo/yr
|
$(-1,560.0) | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $910 | $1,530 |
$514
7,390
kWh
|
$396
-
kW-mo/yr
|
- | - | |
| 04 | 2.3191: Use demand controller or load shedder | $8,492 | $1,950 | - |
$8,492
-
kW-mo/yr
|
- | - | |
| 05 | 4.122: Develop standard procedures to improve internal yields | $3,420 | $1,000 | - | - | $3,420 | - | |
| 06 | 4.321: Optimize production lot sizes and inventories | $666 | $1,000 | - | - | - | $666 | |
| 07 | 4.321: Optimize production lot sizes and inventories | $44,800 | $1,000 | - | - | - | $44,800 | |
| 08 | 4.521: Clear and rent existing space | $240,000 | $25,000 | - | - | - | $240,000 | |
| TOTAL RECOMMENDED | $310,624 | $40,705 |
$7,563
108,806
kWh
|
$15,735
-
kW-mo/yr
|
$1,860 | $285,466 | ||
| TOTAL IMPLEMENTED | $49,013 | $2,725 |
$2,748
39,536
kWh
|
$2,359
-
kW-mo/yr
|
$(-1,560.0) | $45,466 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs